Views: 0 Author: Site Editor Publish Time: 2024-08-09 Origin: Site
Before testing the plastic mixer machine, carefully check whether the connected power supply meets the requirements of the machine. All components are fully installed, and according to the circuit diagram, there are no errors in the circuits connected during installation. Each lubrication point should be filled with the designated lubricating oil and the rust proof oil should be wiped off all parts of the machine.
The mixer should start from no-load start-up, then undergo load testing, and check whether the pneumatic parts are normal and whether the discharge door is properly opened and closed. After trial operation, it will be put into production for use.
After using the machine, if it is not used for a short period of time, the inner wall of the pot and the stirring blade should be carefully wiped clean. When not in use for a long time, rust proof oil should be applied.
Requirements for each lubrication point:
The main shaft of the mixer is lubricated with No. 2 sodium based grease (GB492-65) and refilled once a day.
Full machine maintenance should be carried out every six months, including replacing seals and checking the condition of electrical circuits and components.
Note: When using electric heating at the upper interface, the screw hole should not be blocked for easy ventilation.This machine is not allowed to start with load. Start at low speed without load first, and then add material to the feeding machine.